Key Takeaway
You can check your LADBS permit status online using the Permit and Inspection Report, searching by property address or 15-digit permit number. LADBS only covers the City of Los Angeles; Altadena falls under LA County and Pasadena uses its own portal. Each status label tells you who acts next: the City, your design team, or your contractor. Knowing the difference between PC Approved, Issued, and Permit Finaled keeps your rebuild moving.
To check an LADBS permit, use the official LADBS Permit and Inspection Report and search by your property address or the 15-digit permit/application number. If your rebuild was filed electronically, also check the ePlanLA dashboard for corrections and correspondence. Here’s the idea the rest of this guide leans on: a status label tells you who has the next move, whether that’s the City, your architect, or your contractor. That’s what a fire survivor really needs to know about the rebuild project ahead.
First, confirm LADBS is your permitting authority in Los Angeles City

Before you track anything, make sure you’re in the right system. LADBS only covers the City of Los Angeles, so the authority that handles permit issuance depends on where your property sits.
| Property location | Permit authority |
|---|---|
| Los Angeles City (incl. Pacific Palisades) | LADBS |
| City of Pasadena | Pasadena Permit Center Online |
| Unincorporated LA County (incl. Altadena) | LA County EPIC-LA |
| City of Malibu | Malibu’s own portal |
An Altadena Eaton Fire rebuild is generally a County project, not LADBS. And a City of Pasadena property uses Pasadena’s system, even though our office is in Pasadena.
Which LADBS tool should you use?
Much of the confusion comes from treating these four systems as interchangeable. They aren’t, and knowing which one holds the information you need saves days.
- Permit and Inspection Report: public lifecycle status, clearances, and inspection history for your structures.
- ePlanLA: your active electronic application, corrections, and correspondence (usually needs the applicant’s login).
- PRISM: scanned permits, plans, and Certificates of Occupancy for records research.
- LA Strong Recovery Dashboard: aggregate rebuild progress, not one homeowner’s next step.
How to look up your permit status

You can search two ways: by the 15-digit permit/application number, or by property address. That 15-digit number is the application number before issuance and the permit number after. A separate 10-character plan-check (job) number identifies your plans, and one plan-check number can tie to several permits. A large rebuild shows multiple permits, so make sure you select and read the right one. Note that major rebuilds often carry separate permits for structural, electrical, and plumbing work, and each moves on its own clock.
What each LADBS permit status means (and who acts next)
This is the part most homeowners want. A status is a to-do list with your name, or someone else’s, on it.
| Status | What it means | Who acts next | What to ask for |
|---|---|---|---|
| Submitted | Fees paid, plan check begun | LADBS | Confirmation it’s in queue |
| PC Assigned | A plan-check engineer is assigned | LADBS | Reviewer name |
| Corrections Issued | Items to revise. Not a denial | Your design team | Correction sheet and response matrix |
| Recheck | Revised plans being reviewed | LADBS | Timeline update |
| PC Approved | Plans approved, permit not yet issued | You | Remaining clearances, fees, documents |
| Ready to Issue | Issuance fees remain | You | Fee total |
| Issued | Construction may proceed under approved scope | Contractor | Issued permit, stamped plans, inspection schedule |
| Permit Finaled / CofO Issued | Work and inspections approved | Done | Final inspection record, Certificate of Occupancy |
Two points worth holding onto: “PC Approved” is not “Permit Issued,” and “Issued” is not “Finaled.”
Why an approved plan still may not be an issued permit

A permit can have approved plans and still sit unissued because another required authorization isn’t complete. The report lists each clearance as “Cleared” or “Not Cleared,” and a category can show both when some individual clearances are done and others aren’t. This is where compliance with the full set of City requirements matters. Open the clearance section before you assume plan check is the holdup.
How long your application or permit stays active
Three separate rules cause most of the mix-ups:
- Plan check: normally 18 months from when the plan-check fee is paid, with six-month extensions up to three times (as much as three years from original submission).
- General permit validity (LAMC §98.0602): generally two years, but can expire after 12 months if work hasn’t started or has been inactive for 12 continuous months.
- Fire-rebuild exception: the City’s current Palisades guidance says eligible issued rebuild permits are to be completed within three years, subject to extension.
Ignore the legacy “180 days” wording on old help pages. The current standard is the 12-month rule, with the three-year completion period for eligible fire rebuilds. The exact rule that applies to you can vary depending on when your permit issued.
What to do if your status looks stuck
Work the list calmly. Review ePlanLA for corrections, check the clearance section for “Not Cleared” items, and ask your architect or engineer for the correction response matrix. Then contact the assigned plan checker or inspector. For LADBS help, call 311 inside Los Angeles or (213) 473-3231 outside the City; ePlanLA IT support is (213) 275-3434. If you prefer a written trail, send your question by email so the exchange is documented. An inspection can read “pending” after the inspector visits but before the result posts, so don’t assume a problem. A specialized fire-rebuild contractor should be able to show you the issued permit, stamped plans, outstanding corrections, and inspection results at each milestone. That documentation is part of your rights as the homeowner. A status change should be documented, never used as vague pressure for an unsupported payment.
Keep these records, and work with a licensed fire-rebuild specialist

Hold onto your application and permit numbers, correction sheets and written responses, clearance records, the issued permit and stamped plans, inspection results, and your Certificate of Occupancy or signed completion documents. Together they are the record that protects you if a question comes up later. Golden Coast Construction & Restoration keeps a permanent office in Pasadena serving Southern California fire recovery. Our licensing is verifiable: we’re a California General Contractor (CSLB #838443), IICRC-certified, handling fire restoration through complete reconstruction. We work directly with adjusters, carry construction through each building inspection, and tie milestone payments to documented progress so you can see where the project stands. The complexity of a rebuild is real, which is why an honest scope needs eyes on the property. We invite an on-site assessment. Anyone quoting a firm price sight-unseen is a red flag.
Frequently Asked Questions
How do I check my LADBS permit status online?
Use the Permit and Inspection Report by address or permit number. For an active electronic application, check ePlanLA for the corrections and correspondence tied to your plans. You can find both through the official LADBS portal.
Can construction begin when the status says “PC Approved”?
No. Plans are approved, but the permit isn’t issued yet. Construction may proceed once the status reads “Issued.”
Does “Issued” mean the permit is complete?
No. Complete is “Permit Finaled,” plus a Certificate of Occupancy where required for safety sign-off.
Why are some clearances still marked “Not Cleared”?
Another required authorization from a City department or outside agency isn’t finished. Open the clearance section to learn which one.
Does LADBS handle properties in Pasadena or Altadena?
No. City of Pasadena uses Pasadena’s portal, and Altadena is generally under LA County. These are separate permitting services from the City of Los Angeles.